Madill area, Southern Oklahoma

Voltage: 138 kilovolt

Length: 27 miles

Route: From the existing Caney Creek Substation near Kingston northward to a new Johnston County substation north of Ravia, along the west side of Madill.

Construction Schedule

Right of Way Acquisition and Surveys: 2009

Construction Under Way: 2010

Completion: 2011