Sooner to Cleveland
Voltage: 345 kilovolt
Length: 36 miles
Route: From the existing OG&E Sooner Power Plant substation in Noble County to the existing GRDA Cleveland substation in Osage County.
Right-of-way acquisition and surveys: 2010
Construction: 2011-2012
Information: 1-866-558-2509