 Woodward/Thistle 

 

  

 Woodward to Thistle

Voltage: 345 kilovolt double-circuit

Length: 90 miles

Route: From the existing Woodward EHV substation south of Woodward, Okla., north and east to northeastern Woods County, Okla. to connect to the Thistle substation 

Construction Schedule

Right of Way Acquisition and Surveys: 2011-12

Construction Under Way: 2013-14

Completion: 2014